B. L. Harbert International
2
2nd BCT Barracks Complex
Ft. Campbell, KY
  • Barracks
    • #1: Ready to punch and clean
    • #2: Drywall complete, paint 90%, flooring 60%, millwork complete, mechanical work 95%, electrical work 95%
    • #3: MEP rough-in 95%, drywall 90%, paint 60%
    • #4: MEP rough-in 90%, drywall 30%
  • RSU – Complete
  • Dining Hall
    • Footings complete
    • Crawl space walls complete
    • Mud slab poured
    • Elevated deck poured
    • Slab on grade poured
    • Structural steel 90%
    • MEP in progress
    • Interior and exterior framing in progress
  • Co-ops
    • HHC: Ready to clean and punch
    • BTB: Administration MEP rough-in 95%, drywall complete, paint 90%, readiness interior finishes 90%, laydown canopy in progress
    • BSB: Administration MEP rough-in 75%, drywall 50%, readiness pre-engineered building erection complete, laydown canopy in progress
  • Substation
    • Foundations and pads poured, structural framing 50%
  • TEMF Site Work
    • Grading complete, storm, sewer and water complete, paving 90%, electrical 95%, hardstand DGA complete
3
5th SF Battalion Operations Complex, Phase 3
Ft. Campbell, KY
4
ATB Barracks
Ft. Benning, GA
5
Auburn University New Basketball Arena
Auburn, AL
  • Site utilities and stormwater 50%
  • North elevation foundation wall 95%
  • Administration slab 60%
  • Concourse slab & raker beams 60%
6
Cyberknife Addition to
Brookwood Medical Center
Birmingham, AL
  • Completing interior demolition
  • Completed excavation for the vault
  • Intend to pour vault slab on Nov 11
7
IBCT Battalion HQ Annex
Ft. Knox, KY
  • Landscape and sidewalks 95%
  • Brick punch list 95%
  • Storefront installation 99%
  • Elevator installation 95%
  • Ceramic tile ongoing
  • Finish carpentry ongoing
  • Final paint upcoming
8
IBCT Brigade Dining Facility
Ft. Knox, KY
  • Project is in punch list stage
  • System testing has started and will continue through Nov and Dec
9
IBCT Company Operations Facilities
Ft. Knox, KY
  • Final paving / striping complete
  • Site lighting 45%
  • IB2 – domestic water piping epoxy lining MOD complete, ready for final punch
  • IB1 – domestic water piping epoxy lining MOD underway
  • FA – QA punch complete, awaiting epoxy lining MOD
  • STB – QA punch complete, awaiting epoxy lining MOD
  • BDE / RSTA – QA punch 98%, awaiting epoxy lining MOD
10
Science & Engineering Complex
University of Alabama
Tuscaloosa, AL
  • Exterior skin 90%
  • Drywall hanging 95%
  • Interior finishes progressing throughout the building
11
Shades Creek Office Building
Birmingham, AL
  • Structural steel erected and all structure concrete poured
  • Exterior framing and sheathing started
  • Interior MEP rough started
  • Working on site walls and utilities
12
Shades Mountain Dam Rehabilitation
Birmingham, AL
13
SOF Battalion Operations Complex – Phase II
Fort Campbell, KY
  • Drywall 90%
  • Painting 60%
  • Ceramic Tile 65%
  • Ceiling grid 30%
  • Above ceiling rough-in 80%
  • C Company Addition 20%
14
Unit Operations Facility
Ft. Stewart, GA
  • Med TEMF
    • Steel structure complete
    • Roof panels started
    • Mason has started on exterior CMU
    • Vault structure complete
  • Barracks
    • Foundations 60%
    • Curb and gutter installation 70%
    • Concrete paving 20%
  • COF Complex
    • Foundations of COF and Readiness building complete
    • Readiness building slab on grade and vault walls complete
  • Small TEMF excavation and backfill for foundations 85%
15
New Embassy Compound
Addis Ababa, Ethiopia
  • Preparing subgrade at MSGQ
  • Pouring walls GSX
  • Continuing duct bank installation
  • NOB excavation
  • Pouring walls and footers NOB
  • Pre-casting and setting electrical manholes
  • Tower crane installation ongoing
  • Mixing test mixes at the BLHI batching plant
16
New Embassy Compound
Antananarivo, Madagascar
  • Site Utilities
    • Segmental retaining wall 75%
    • Perimeter wall north 28%
    • Electrical duct banks 35%
    • Telecom duct banks 41%
    • Site storm water installation 65%
    • Site sanitary sewer installation 51%
    • Site domestic water installation 29%
    • Site fire water installation 16%
    • Fuel tanks & fuel piping 47%
  • NOB Building
    • Grade beams & pile caps 100%
    • 1st floor structural slab 100%
    • 1st floor walls 62%
    • 1st floor columns 100%
    • 1st floor interior walls 27%
    • 2nd floor slab 28%
    • 2nd floor walls 7%
  • CAC / Utility Building
    • Piling 91%
    • Basement walls 51%
  • GSX Building
    • Piling 72%
    • Grade beams 7%
17
U. S. Embassy
Brazzaville, Republic of Congo
  • All buildings 100% complete with punchlist
  • Working on clearing punchlist items for all buildings and all areas
  • Final site grading, landscaping, and grass seeding 86%
  • Temporary ACF demolition complete
  • OBO Accreditation pending USG team arrival on site
  • Final commissioning and training for all equipment and systems 96%
18
U. S. Consulate Compound
Johannesburg, South Africa
19
U.S. Embassy Compound
Karachi, Pakistan
  • Temp facilities - 100%
  • NOB - 20%
  • SCAC - 50%
  • RCAC - 50%
  • Demarc Bldg - 10%
  • Utility Bldg #1 – 5%
  • Underground tanks -90%
  • Site utilities - 75%
20
New Embassy Compound
Lusaka, Zambia
  • PROJECT DESIGN:
    • Building Permit Package Submitted to Lusaka City Council 22SEP08
    • Package 1-100% Submitted to OBO 14OCT08
    • Package 2-35% Submitted to OBO 14OCT08
    • The DD Presentation was held 16OCT08

  • ACTIVITY ONSITE:
    • Site Surveying and Confirmation of Boundary Points
    • Site Clearing and Temporary Erosion Control Measures
    • Construction of ACF, BLHI Offices, OBO Offices, Warehouse, and Sallyport
    • Borehole Completed for Construction Water Requirements
    • Offloading of Material and Equipment Shipments
    • Coordination with Municipal Utility Providers
    • Preparatory Work for Set-up of Concrete Batch Plant
21
New Embassy Compound
Ouagadougou, Burkina Faso
  • STRUCTURES: (% COMPL.)
    • NOB: 75%
    • UTL:  85%
    • CCAC: 95%
    • MCAC: 90%
    • SCAC: 35%
    • DEMARC: 10%
    • REC: 15%

  • UNDERGROUND UTILITIES
    • STORM: 90%
    • ELECT.: 90% (CONDUIT)
    • TSS: 65% (CONDUIT)
    • DOMESTIC: 65%
    • FUEL OIL: 65%
    • FIRE: 55%
    • SANITARY: 45%

  • NOB ABOVE CEILING ROUGH-IN (START DATE):
    • SANITARY:25AUG
    • STORM: 25AUG
    • DUCT: 01SEP
    • DOMESTIC: 05SEP
    • FIRE: 08SEP
    • PULL WIRE: 10SEP


22
U.S. Embassy Compound
Khartoum, Sudan
  • Starting drywall in the CCAC and MCAC
  • NOB ductwork and FP 70%
  • NOB 2nd CAA duct and metal studs started
  • All underground structures 95%
  • GSX foundations underway, erect steel package in Feb
  • Permanent construction in UTL at 75%
  • Plaster started CCAC
  • OBO and BLHI moving into new Temp Offices
23
Winder Consolidated Health &
Salomon Dental Clinic
Fort Benning, GA
  • Dental Clinic Addition
    • Finishing up detention pond
    • Beginning site demolition and grading
    • Starting foundations in next two weeks
  • Health Clinic
    • Moving trailers to continue fill operations
    • Starting foundations in two weeks