- Barracks
- #1: Ready to punch and clean
- #2: Drywall complete, paint 90%, flooring 60%, millwork complete,
mechanical work 95%, electrical work 95%
- #3: MEP rough-in 95%, drywall 90%, paint 60%
- #4: MEP rough-in 90%, drywall 30%
- RSU – Complete
- Dining Hall
- Footings complete
- Crawl space walls complete
- Mud slab poured
- Elevated deck poured
- Slab on grade poured
- Structural steel 90%
- MEP in progress
- Interior and exterior framing in progress
- Co-ops
- HHC: Ready to clean and punch
- BTB: Administration MEP rough-in 95%, drywall complete, paint 90%,
readiness interior finishes 90%, laydown canopy in progress
- BSB: Administration MEP rough-in 75%, drywall 50%, readiness
pre-engineered building erection complete, laydown canopy in progress
- Substation
- Foundations and pads poured, structural framing 50%
- TEMF Site Work
- Grading complete, storm, sewer and water complete, paving 90%,
electrical 95%, hardstand DGA complete
|
|
3
|
|
|
4
|
|
|
5
|
- Site utilities and stormwater 50%
- North elevation foundation wall 95%
- Administration slab 60%
- Concourse slab & raker beams 60%
|
|
6
|
- Completing interior demolition
- Completed excavation for the vault
- Intend to pour vault slab on Nov 11
|
|
7
|
- Landscape and sidewalks 95%
- Brick punch list 95%
- Storefront installation 99%
- Elevator installation 95%
- Ceramic tile ongoing
- Finish carpentry ongoing
- Final paint upcoming
|
|
8
|
- Project is in punch list stage
- System testing has started and will continue through Nov and Dec
|
|
9
|
- Final paving / striping complete
- Site lighting 45%
- IB2 – domestic water piping epoxy lining MOD complete, ready for final
punch
- IB1 – domestic water piping epoxy lining MOD underway
- FA – QA punch complete, awaiting epoxy lining MOD
- STB – QA punch complete, awaiting epoxy lining MOD
- BDE / RSTA – QA punch 98%, awaiting epoxy lining MOD
|
|
10
|
- Exterior skin 90%
- Drywall hanging 95%
- Interior finishes progressing throughout the building
|
|
11
|
- Structural steel erected and all structure concrete poured
- Exterior framing and sheathing started
- Interior MEP rough started
- Working on site walls and utilities
|
|
12
|
|
|
13
|
- Drywall 90%
- Painting 60%
- Ceramic Tile 65%
- Ceiling grid 30%
- Above ceiling rough-in 80%
- C Company Addition 20%
|
|
14
|
- Med TEMF
- Steel structure complete
- Roof panels started
- Mason has started on exterior CMU
- Vault structure complete
- Barracks
- Foundations 60%
- Curb and gutter installation 70%
- Concrete paving 20%
- COF Complex
- Foundations of COF and Readiness building complete
- Readiness building slab on grade and vault walls complete
- Small TEMF excavation and backfill for foundations 85%
|
|
15
|
- Preparing subgrade at MSGQ
- Pouring walls GSX
- Continuing duct bank installation
- NOB excavation
- Pouring walls and footers NOB
- Pre-casting and setting electrical manholes
- Tower crane installation ongoing
- Mixing test mixes at the BLHI batching plant
|
|
16
|
- Site Utilities
- Segmental retaining wall 75%
- Perimeter wall north 28%
- Electrical duct banks 35%
- Telecom duct banks 41%
- Site storm water installation 65%
- Site sanitary sewer installation 51%
- Site domestic water installation 29%
- Site fire water installation 16%
- Fuel tanks & fuel piping 47%
- NOB Building
- Grade beams & pile caps 100%
- 1st floor structural slab 100%
- 1st floor walls 62%
- 1st floor columns 100%
- 1st floor interior walls 27%
- 2nd floor slab 28%
- 2nd floor walls 7%
- CAC / Utility Building
- Piling 91%
- Basement walls 51%
- GSX Building
- Piling 72%
- Grade beams 7%
|
|
17
|
- All buildings 100% complete with punchlist
- Working on clearing punchlist items for all buildings and all areas
- Final site grading, landscaping, and grass seeding 86%
- Temporary ACF demolition complete
- OBO Accreditation pending USG team arrival on site
- Final commissioning and training for all equipment and systems 96%
|
|
18
|
|
|
19
|
- Temp facilities - 100%
- NOB - 20%
- SCAC - 50%
- RCAC - 50%
- Demarc Bldg - 10%
- Utility Bldg #1 – 5%
- Underground tanks -90%
- Site utilities - 75%
|
|
20
|
- PROJECT DESIGN:
- Building Permit Package Submitted to Lusaka City Council 22SEP08
- Package 1-100% Submitted to OBO 14OCT08
- Package 2-35% Submitted to OBO 14OCT08
- The DD Presentation was held 16OCT08
- ACTIVITY ONSITE:
- Site Surveying and Confirmation of Boundary Points
- Site Clearing and Temporary Erosion Control Measures
- Construction of ACF, BLHI Offices, OBO Offices, Warehouse, and
Sallyport
- Borehole Completed for Construction Water Requirements
- Offloading of Material and Equipment Shipments
- Coordination with Municipal Utility Providers
- Preparatory Work for Set-up of Concrete Batch Plant
|
|
21
|
- STRUCTURES: (% COMPL.)
- NOB: 75%
- UTL: 85%
- CCAC: 95%
- MCAC: 90%
- SCAC: 35%
- DEMARC: 10%
- REC: 15%
- UNDERGROUND UTILITIES
- STORM: 90%
- ELECT.: 90% (CONDUIT)
- TSS: 65% (CONDUIT)
- DOMESTIC: 65%
- FUEL OIL: 65%
- FIRE: 55%
- SANITARY: 45%
- NOB ABOVE CEILING ROUGH-IN (START DATE):
- SANITARY:25AUG
- STORM: 25AUG
- DUCT: 01SEP
- DOMESTIC: 05SEP
- FIRE: 08SEP
- PULL WIRE: 10SEP
|
|
22
|
- Starting drywall in the CCAC and MCAC
- NOB ductwork and FP 70%
- NOB 2nd CAA duct and metal studs started
- All underground structures 95%
- GSX foundations underway, erect steel package in Feb
- Permanent construction in UTL at 75%
- Plaster started CCAC
- OBO and BLHI moving into new Temp Offices
|
|
23
|
- Dental Clinic Addition
- Finishing up detention pond
- Beginning site demolition and grading
- Starting foundations in next two weeks
- Health Clinic
- Moving trailers to continue fill operations
- Starting foundations in two weeks
|