B. L. Harbert International
2
New Embassy Compound
Addis Ababa, Ethiopia
  • Accreditation of NOB is scheduled for July 23, 2010
  • Continuing irrigation and landscaping
  • Telephone and data cabling completed and tested
  • Punching out furniture
  • Installing TSS
  • Installing stone cladding on MCAC, CCAC and pavers
  • Testing and commissioning equipment
  • Installing glass handrails
  • Installed RMS
3
AMC / USASAC Headquarters
Redstone Arsenal, AL
4
Archive Building for USASOC Historian
(SRS – BLH Joint Venture)
Ft. Bragg, NC
  • Poured slab on grade Feb 19
  • Started structural metal exterior wall framing on Feb 22
  • Started installation of pre-fabricated metal trusses on March 2 – activity currently in progress
  • Expected completion of roof trusses and plywood sheathing is Mar 9
  • All sitework and storm water drainage management activities are completed
5
BTC II – Barracks / Company Ops Facility
Ft. Jackson, SC
  • Barracks 1
    • Punch & testing stage
  • Barracks 2
    • Paint – 95%
    • Flooring – 100%
    • MEP trim out – 95%
    • Punch and testing started
  • Barracks 3
    • Paint – 90%
    • Flooring – 100%
    • Misc. arch specialties – 95%
    • MEP trim out – 90%
6
Child Development Center
Ft. Campbell, KY
  • Sitework
    • Grading – 80%
    • Storm water system – 50%
    • Electrical & communication duct bank – 80%
    • Water supply – 80%
  • Building
    • Exterior framing and sheathing – 100%
    • Interior block – 100%
    • Exterior brick / block – 30%
    • Interior framing – 60%
    • Decking – 100%
    • Roof – 10%
7
U.S. Consulate Compound
Dubai, United Arab Emirates
  • NOB ------- 55%
  • CCAC ----- 40%
  • MCAC ----  40%
  • SCAC ----- 60%
  • Garage --- 75%
  • Utility ------ 50%
  • Site -------- 50%
8
JSF Academic Training Center
Eglin AFB, FL
  • Concrete access drivers and base course of asphalt are complete in the courtyard
  • Carpeting and final paint in the north wing are 10%
  • TAB in the north wing is 70%
  • Ceiling grid is 90% complete throughout; ceiling tiles are 60% installed
  • Terrazzo is 100% installed, 50% ground / polished
9
U.S. Embassy Compound
Karachi, Pakistan
  • NOB - 97%
  • CCAC – 100%
  • RCAC – 100%
  • SCAC – 99%
  • MCAC – 99%
  • GSX – 98%
10
New Embassy Compound
Kyiv, Ukraine
  • Concrete / Structural Work
    • NOB – 79%
    • MSGQ – 9%
    • MCAC – 27%
    • SCAC – 0%
    • CCAC – 100%
    • UTL – 90%
    • SPX – 0%
    • PKG – 67%
    • Perimeter Wall – 44%
    • Underground utilities (MH, Ductbanks, etc.) – 93%
11
New U.S. Embassy Compound
Lusaka, Zambia
  • PROJECT DESIGN:
    • Issued For Construction: 31st March, 2009


  • ACTIVITIES ONSITE:
  • Commissioning
    • Permanent Power systems complete.
    • Fire Pump startup complete
    • HVAC system start up begins in May
    • Fuel Oil System start up begins in June
    • Domestic Water start up begins in June


  • CMPD
    • WWTP operational
    • Curb / Gutter 85% complete
    • Unit pavers 25% complete
    • Landscaping 35% complete
    • BLHI / OBO will relocate to offsite offices in May


  • Finishes
    • NOB – Final above ceiling punch list underway
    • NOB – Final Room punch lists underway
    • Out Buildings – Final punch lists underway
    • Telecom build out started in May
    • TSS scheduled to begin in June


12
Maneuver Center HQ Expansion
Ft. Benning, GA
  • Design ongoing
  • P1 – site grading / utilities design 100%
  • P2 – structural & underground design 100%
  • P3 – architectural and MEP 60% review
  • Site mobilization commenced
13
New U.S. Embassy Compound
Monrovia, Republic of Liberia

  • ONGOING ACTIVITIES:
    • Blasting for Site Utilities
    • Rock Crushing and Stockpiling Onsite
    • Site Fill Operations
    • Manholes and Underground Site Utilities
    • Site Retaining Walls
    • NOB – Level 4 Elevated Slab
    • NOB – MEP Rough-ins Level 1 & 2
    • UTL – Roof Parapets
    • SCAC – MEP Rough-ins
    • MCAC – Foundations and Exterior Walls
    • MSGQ – Level 2 Elevated Slab
    • WHE – Foundations


14
Rotary Wing HQ and Hangar Facility
Redstone Arsenal, AL
  • Hangar
    • SOG – 50%
    • Steel erection – 95%
    • Roofing – 75%
    • Exterior masonry – 20%
    • Site demolition, clearing & grubbing, and grading – 95%
    • Offsite utilities – 50%
  • Headquarters
    • SOG & SOD – 100%
    • Exterior metal framing and sheathing – 75%
    • Interior O/H MEP R/I – 30%
    • Site grading – 95%
    • Parking lot – 95%
15
Shades Mountain Filter Plant Phase II Upgrade
Birmingham, AL
  • Concrete for the base slab of Clear Well Tank #2 placed on May 28th
  • Crom Corporation is installing formwork for Baffle Walls on Clear Well Tank #2
  • Continuing to construct foundation walls for Finished Water Pump Station
  • Electrician continuing to install underslab conduits at Finished Water Pump Station
  • Continuing to install various sizes of Ductile Iron Pipe
16
Warrior in Transition Complex
Ft. Benning, GA
  • Initial phase of E&S complete
  • Clear and grub – 20%
  • Design package 1 – IFC
  • Design package 2 – IFC
  • Design package 3 – 100%
17
Warrior in Transition Barracks
Ft. Knox, KY
  • Project kick-off meeting with the Corps on May 14